Critical path
Find how soon a project can finish when independent jobs can run together. Identify a chain of jobs where any delay holds up the whole project.
Each arrow is a job. Its number tells you how many days it takes. Record the latest prerequisite finish at each vertex. Trace back from the last event to see a chain that determines the project duration.
Time is O(V + E). A cycle prevents a schedule.